Your new mold has arrived — and it does not fit your press. The locating ring is the wrong size, the mold is taller than your daylight allows, or the hot-runner connector does not match your controller.
An export mold will run on your machines only if three things are settled before design release: the press data is sent with the RFQ, one mold standard is agreed, and the acceptance evidence and handover package are defined in writing. Miss any one of them, and the mold may arrive as a crate you cannot use.
This guide covers the three in order — press fit, the machine-data sheet, the mold standard, acceptance evidence, and the handover package.
Why buying a mold to run at home is a different purchase
When you buy molded parts, the supplier owns the fit problem: the mold runs on the supplier’s presses, water, power, and maintenance routines. When you buy the mold itself, the fit problem moves to your plant — and the mold is built to the data you supply. If that data is missing or wrong, the mismatch is discovered at installation, when fixing it costs the most.
Three decisions therefore move to the buyer before the build starts: compatibility, acceptance, and handover — whether the tool fits your press, what evidence you require before it ships, and what arrives with it so your team can run and maintain it. The build itself follows the same steps as any mold — technical review, DFM approval, machining, trial, and delivery support, as described on our mold-making page — but for an export tool, the buyer’s inputs at the start decide whether the end works.
Will it fit your press? The checks that decide it
Seven interfaces decide whether a mold fits a press, and most are fixed at design release — which is why they belong in the RFQ, not in a conversation after the mold is built.
Clamp tonnage. The press must hold the mold closed against injection pressure over the part’s projected area. Send your press tonnage in the RFQ; the required force is checked during design review against the part, cavity count, and resin.
Platen size and tie-bar spacing. The mold must pass between the tie bars and sit fully on both platens. Send the platen dimensions and the tie-bar spacing — a mold wider than the clearance cannot be installed at all, regardless of tonnage.
Mold height and daylight. The closed mold height must sit within the press’s minimum and maximum mold height, and the opening stroke must leave room for the part to clear the core on ejection. Height is set by the plate stack and cannot be corrected at installation.
Shot capacity. The total shot weight — all cavities plus the runner — must sit within the press’s rated shot capacity. Send the rated capacity and the resin it was rated with, because capacity in grams depends on the material.
Nozzle and locating ring. The nozzle radius must seat against the sprue bushing, and the locating ring diameter must match the register bore in the fixed platen. These two dimensions are set by the mold standard and the press, and they are the most common small mismatch.
Ejection. The ejector pattern, stroke, and type — mechanical rods or hydraulic ejection — must match the mold’s ejector plate, and the ejectors must return fully before the mold closes.
Utilities and controls. Cooling connections and flow, electrical supply, hydraulic circuits for core pulls, and — where the mold has one — the hot-runner controller brand, connector type, and thermocouple type must match what your plant provides.
Illustrative example — assume a press with a maximum mold height of 400 mm and a mold built at 450 mm closed height. The mold cannot be installed on that press, and the correction is a new mold base or a different press. The numbers are an example with stated assumptions, not a quotation: height is decided at design, not at installation.
| Press-fit check | What the buyer sends | What fails if it is missing |
|---|---|---|
| Clamp tonnage | Press tonnage | Mold flashes or cannot be held closed |
| Platen size and tie-bar spacing | Platen dimensions, tie-bar spacing | Mold cannot be installed between tie bars |
| Mold height and daylight | Minimum and maximum mold height, opening stroke | Mold too tall, or part cannot clear the core |
| Shot capacity | Rated shot capacity and resin | Incomplete shot or inconsistent plasticizing |
| Nozzle and locating ring | Nozzle radius, locating ring diameter | Nozzle cannot align with the sprue bushing |
| Ejection | Ejector type, pattern, stroke | Mold cannot eject on this press |
| Utilities and controls | Cooling, electrical, hydraulic, hot-runner controller details | Mold cannot be cooled, heated, or controlled |
The machine-data sheet to send with your RFQ
Fill in this sheet before the RFQ goes out. If a field is unknown, say so — the mold maker can advise on it, but cannot guess it. Treat the sheet as a controlled input: a change after design release is a design change.
| Machine data | Your entry |
|---|---|
| Press make and model | |
| Clamp tonnage | |
| Platen size (width × height) | |
| Tie-bar spacing (horizontal × vertical) | |
| Minimum / maximum mold height | |
| Daylight / opening stroke | |
| Maximum shot capacity (state resin and unit) | |
| Screw diameter (if known) | |
| Nozzle radius | |
| Locating ring diameter | |
| Ejector type, pattern, and stroke | |
| Cooling connections (number, size, type) | |
| Electrical supply | |
| Hot-runner controller brand and connector | |
| Hydraulic circuits (for core pulls, if any) | |
| Preferred mold standard (DME / HASCO / LKM / customer standard) | |
| Plant location and delivery address |
A supplier who quotes an export mold without asking for this sheet is quoting a mold for their own press, not for yours. The sheet also makes quotes comparable: two quotes built to the same press data and standard can be compared on scope; two built to different assumptions cannot.
Which mold standard should you specify?
A mold standard is a catalog system for the mold base and its components — the plates, leader pins, bushings, ejector parts, and screws that hold the cavity and core and keep the two halves aligned every cycle. Three systems dominate the world market: DME, which is imperial and North American; HASCO, which is metric and European; and LKM, which is used widely in Asia. Each publishes catalog grids of footprints and plate thicknesses, so a designer picks a frame that fits the part envelope and machines only what the application needs. This DME’s mold-base page sets out its A-Series and B-Series bases, plate stack-ups and sizes — the imperial North American system.
The standard decides more than dimensions. It also locks in the screw patterns, leader-pin diameters, and ejector conventions, so spares stay available years into the tool’s life. That is the practical reason to choose the system your plant already stocks and maintains: a plant that stocks HASCO spares should not receive a DME tool unless it accepts the spares consequence. Choose one system per tool and state it in the RFQ and on the drawings.
State your standard early. Technical review is the first step of every build on our mold-making page, and that review covers the CAD, drawing, resin, volume, finish, tolerances, timing, and any customer standard — so a stated standard is reviewed before machining, not discovered afterwards. If your plant has its own standard, send the specification with the RFQ rather than naming it in a later email.
What acceptance evidence to require before the mold ships
Acceptance is a decision, not a photograph. Agree the evidence list before the build starts, and require it against the same mold revision being shipped — a report for an earlier revision does not approve the tool in the crate.
Agree trial stages first, because naming varies by customer. A T0 trial is an early internal engineering run confirming basic mold movement, filling, and ejection; a T1 trial is the first structured customer-sample trial after the mold is sufficiently complete. Confirm what each name means in the project plan, what sample quantity each stage produces, and what reporting each requires. Our mold-making scope runs a T1 trial and reviews filling, cooling, appearance, dimensions, fit, ejection, and function before any correction decision.
The evidence package for shipment release should include the trial records, the sample status, the molding-condition references, the critical-dimension results — measured, for example, by CMM — and the first-article inspection records. The exact list is a project agreement, but write it down before the build, not after the samples arrive. If you cannot attend the trial, require the full evidence package and the signed acceptance report before shipment release; photos alone do not show dimensions, cavity variation, or process stability.
Our injection mold inspection checklist sets out the final release checks behind that report: corrections closed, spare parts delivered, the mold clean and protected, water lines drained or preserved, the data package complete, and the acceptance report signed. Ask for the checklist result, not only the sample parts. A useful cross-check on the evidence package is Protolabs’ injection moulding inspection page, which sets out the reports a buyer can require before release — partial first-article inspection, dimensional capability studies and PPAP — with the measurements and sample plan for each.
The handover package: what must arrive with the mold
The handover package is what makes the mold maintainable after the builder’s involvement ends. Require it as a condition of shipment, and check it against this list when the crate arrives.
| Handover item | What to check |
|---|---|
| Approved 2D drawing and 3D mold design | Current revision, matching the shipped mold |
| Bill of materials and steel / hardness documents | Steel grades and heat treatment recorded |
| Trial records and sample status | T1 records, corrections, and the approval point |
| Dimensional report and first-article records | Critical dimensions measured, not estimated |
| Process parameter sheets | Starting point only — settings were proven on the builder’s press and may need adjustment on yours |
| Waterline and interface diagrams | Cooling circuits, connections, and labeling |
| Spare-parts list with part numbers | Wear items and replaceable inserts identified |
| Maintenance and lubrication instructions | Cleaning, lubrication, and inspection intervals |
| Rust prevention and packing evidence | Preservation applied, crate condition documented |
| Shipment-release file and signed acceptance report | Release signed against the shipped revision |
One warning on the parameter sheets: they are a reference for the tested machine, resin, and mold condition, not a promise that the same settings will work on your press. Parameters may need adjustment when the mold moves to a different press, material lot, or production environment, so treat the first runs at your plant as a verification run, not a repeat of the builder’s trial.
Spares and maintenance: who is responsible after delivery
Decide this before shipment, in writing. Our mold-making page states it plainly: ownership, spare parts, maintenance responsibility, sample approval, and change costs should be written into the current commercial documents. A mold that arrives without that agreement arrives with an open question about who pays for the first worn ejector pin.
Define the spares list from the approved mold design and your maintenance requirements. Typical items are replaceable inserts, ejector components, sliders, lifters, and other wear parts; where the mold has a hot runner, heaters and thermocouples belong on the list too.
Maintenance is routine work done well: cleaning, lubrication, inspection access, and preservation between runs. The mold should be designed for it — cleaning, wear-part replacement, inspection access, and future modifications are part of the design review, not an add-on. Treat mold-life claims with care: a specific shot-life promise is not made without reviewing the part, resin, tooling construction, cycle conditions, and maintenance plan. A shot life quoted without that review is unconfirmed.
Frequently asked questions
Can we change the mold standard after design release?
Some components can be changed, but the base, screw patterns, and interfaces are set at design release. Changing the standard later usually means rework or a new base, so agree it before DFM approval rather than after machining has started.
What if we replace the press after the mold is built?
Re-check the machine-data sheet against the new press. The locating ring, nozzle, ejector pattern, and hot-runner controller are the usual mismatches. That is what the handover package is for: the drawings and interface diagrams let your team run the check without going back to the builder.
Do we have to use the same resin grade the trial used?
The trial evidence is tied to the grade that was run. Changing the grade changes shrinkage, filling, and appearance, so confirm the change with a new trial or a documented review before committing production volumes to it.
Send the part files and your press data
If you are buying a mold to run in your own factory, send the inquiry through our contact page or email jerry@cavitymold.com. Include the STEP file and the 2D drawing with its revision, the resin grade, the annual volume, the completed machine-data sheet above, your preferred mold standard, the delivery region, and the target timing. The contact form has no secure file upload, so send CAD files by email after the initial reply. A mold quoted against your actual press data is a mold you can install.